The project has a total investment of 215 million USD invested by Export Credit financed from China Bank with a capital of 143 million USD; Loan from Bank for Investment and Development of Vietnam is 25 million USD and Client’s owned capital is 47 million USD.
So far, in the attempt, the effort, determined from units involved in the project, basically components of An Khanh Thermal Power Project have been completed, single-commissioning and inter-lock commissioning under load and off-load was ongoing.
As planned, in 2nd quarter of 2015, An Khanh 1 Thermal Power Plant will connect to the national power system with the capacity of more than 800 million KW/h/year.
Some photos of An Khanh 1 Thermal Power Plant
Boiler and auxiliary system
Turbine and generator
Centre controlling room – supervised by PECC1’s personnel’s for operation and commissioning