In this project, EVNPECC1 plays important roles in supporting contract management for EVN, the Project’s Owner, according to the contracted package No. 8 (TV08-QT1), including:
• Review Consultant: To review the technical design and construction drawing design.
• Supervision Consultant: To supervise the construction quality, schedule, works’ volume, and the health, safety and environment (HSE) factors.
• Contract Management: To be responsible for reviewing contract-related documents, reviewing commercial and legal issues, and coordinating the negotiations with relevant contractors and parties.
By the end of August 2024, the project has achieved a total schedule of 67.55%, of which:
• Design: Completed 93.16%
• Procurement: Achieved 83%
• Construction: Achieved 23.83%
Schedule Plan:
It is expected that, although the Power Planning 8 was approved 2 years late, the project will still maintain the schedule with the commercial power generation milestone of unit 1 in May 2026 and unit 2 in October 2026, meeting the EVN's requirements on the schedule.
Accompanying Vietnam Electricity, EVNPECC1’s engineers have been working day and night to overcome all difficulties and challenges, closely coordinating with relevant units, striving to complete the Project in 2026. Also in recent time, the Company has completed the Feasibility Study Report for the O Mon IV thermal power project, demonstrating EVNPECC1's continuous efforts in contributing to the development of the energy industry and the national economy.